Project Info
CSKT Division of Engineering and Water Resources Active Projects - Irrigation Infrastructure |
* all Engineering and Contractor service requests will be advertised in the Char-Koosta News for at least 3 weeks |
BIA WIIN ACT funding | ||||
Active Projects |
Status |
Engineer |
Contractor |
|
Jocko K Diversion | Construction onsite | McMillen Jacobs | Dick Anderson | |
Tabor Diversion | Engineering | McMillen Jacobs | not bid | |
Tabor Liner | Pre-engineering | McMillen Jacobs | not bid | |
NF Jocko Bridge | Final Design | McMillen Jacobs | not bid | |
Falls Creek Diversion | Final Design/Permitting | WWC Engineering | not bid | |
31A Canal Chute | Design Engineering | WWC Engineering | bidding | |
Bureau of Reclamation Project List |
||||
FRPP Scoping Study | Final Review Ongoing | Reclamation | Reclamation | |
FRPP General Services | Active - Developing New Projects | Reclamation | Reclamation | |
FRPP Shaft Alignment | Active - | Reclamation | K&N Electric | |
Completed Projects |
||||
Flathead River Pumping Plant - Electrical Safety Upgrades | Completed June 2021 | HDR Engineering | Third Element | |
FRPP LIDAR Survey | Completed June 2021 | CSKT | DJ&A | |
COMPACT Funding |
||||
Year 1 - 2021 | ||||
Task 1 | Jocko Canals - North System - K Canals and Lower S | Final Design Phase 1 & 2 | Morrison Maierle | not bid |
Task 2 | Tabor Diversion and Feeder Canals Rehab and Betterment | Pre-Engineering | McMillen Jacobs | not bid |
Task 3 | Lower J Diversion Rehab and Betterment | Final Design/ 90% drawings of Mitigation | DOWL | not bid |
Task 4 | Charlo Delivery Area Modernization - R&B | Preliminary Alternatives | DOWL ITRC | not bid |
DRAFT Finding of No Significant Impact.docx
Popular 18.59 KB |
04/24/2023 09:10:13 | |
DRAFT Jocko Canals Environmental Assessment.pdf
Popular 28.82 MB |
04/24/2023 09:10:13 | |
Notice of Availability.docx
Popular 41.1 KB |
04/24/2023 09:10:13 |